How it is put together
A draw is measured against the schedule of values. For each line it shows:
- the scheduled value, plus approved change orders
- work billed on previous draws
- work this period
- completed to date and percent complete
- balance to finish
- retainage or holdback
In the US, many owners and lenders use the AIA G702 and G703 forms or a lender's own layout. Lenders often send an inspector to confirm progress before releasing funds.
Worked example
One budget line, framing, with 10% holdback on this period's work:
| Framing | Amount |
|---|---|
| Scheduled value | $60,000 |
| Previous draws (30% complete) | $18,000 |
| This period (now 50% complete) | $12,000 |
| Completed to date | $30,000 |
| Balance to finish | $30,000 |
| Holdback: 10% of $12,000 | - $1,200 |
| Due this draw | $10,800 |
Common mistakes
- Billing ahead of progress. An inspector who finds framing 40% complete, not 50%, will cut the draw or return it.
- Missing backup. Every billed line should have its invoices, and the lender may require lien waivers or a statutory declaration.
- Figures that don't tie to the budget. Completed to date plus balance to finish must equal the revised scheduled value on every line.
- Leaving out approved change orders, or billing ones that aren't approved yet.
Related terms
- Schedule of values (SOV): A schedule of values (SOV) is a breakdown of a construction contract or loan budget into line items, each with a dollar value, that together add up to the contract sum.
- Retainage (holdback): Retainage is a percentage of each progress payment that the owner or contractor holds back until the work is complete, to protect against unfinished work and unpaid subcontractors.
- Lien waiver (statutory declaration): A lien waiver is a document in which a contractor, subcontractor or supplier gives up its right to file a lien on a property for amounts it has been paid.
- Change order: A change order is a written amendment to a construction contract that changes the scope of work, the price, the schedule, or all three, agreed by both parties.